Delivering Collahuasi improvements

Faced with increased production demands, Chilean copper miner Compañía Minera Doña Inés de Collahuasi had the goal of increasing both the availability and performance of its vertical plate pressure filters (VPA) in Puerto Patache. 

In collaboration with Metso, Collahuasi developed an upgrade plan aimed at improving the performance of the equipment, as it was outdated after more than 20 years of operation. 

With an upgrade plan based on state-of-the-art technology, the desired objectives were met and resulted in a 15 per cent increase in filter availability.

The project was carried out at Collahuasi’s mine in northern Chile, about 180km south-east of the port of Iquique at an altitude of 4400m. This mining district has been in business since 1880 with the exportation of high-grade copper-silver vein systems. Currently it is dedicated to the extraction and production of copper and molybdenum concentrate.

During 2016, Collahuasi was the third-largest copper operation in the world and had one of the largest deposits of mineral resources of copper on the planet (9.964 million tonnes). Its shareholders are Anglo American (44 per cent), Glencore (44 per cent) and Japan Collahuasi Resources B.V. (12 per cent).

Collahuasi was facing the great challenge common to many global mining groups – optimising its operations to achieve the highest levels of efficiency.

“In order to ensure productivity and profitability in the future, Collahuasi decided to develop a preventive maintenance improvement program,” Collahuasi Processes Vice President Dalibor Dragicevic said.

“This is comprised of a master plan to maximise availability and minimise bottlenecks through a long-term and sustainable approach. Its objective is to detect potential problems in advance and maximise the performance and availability of existing equipment.”

In addition to the VPA filters, Collahuasi has other equipment from Metso, such as semi-autogenous grinding mills, ball mills and vertimills.

Ageing equipment poses a challenge

Thanks to the collaborative relationship between Collahuasi and Metso, a joint diagnostic meeting was held to review the main needs and potential improvement to the filtrate-concentrate level, which was related to the requirements of its VPA vertical filters to increase their production capacity while also increasing the overall reliability of the system.

Due to the high productivity requirements and over 20 years of use since installation, the filters were showing a high degree of wear and misalignment, which reduced their availability due to the extra required maintenance and considerable unplanned downtime.

During the review stage of the overhaul, a joint decision was made to make improvements and upgrade the control systems, lubrication and structure of the equipment in order to achieve higher levels of availability.

Equipment refurbished to as-newcondition

The challenge for Metso was upgrading the control systems to the latest technology, achieving values of over 92 per cent availability and 100 per cent of design capability.

This involved reinstalling and upgrading equipment in less than 20 days in order to minimise lost production. The engineering coordination, parts procurement and planning activities began six months earlier in order to ensure the complete compatibility and successful outcome of this upgrade.

Comprehensive technological solution and successful results

The extensive upgrade of the equipment involved multiple steps. The Metso team first proposed improving the original design capacity by updating components and systems to produce some important benefits.

For this, Metso focused on the main problems causing the structural misalignment of the filters. In order to solve the structural problems, the filter was completely disassembled and over 80 per cent of its parts were replaced with new parts using a nanocoating technology for corrosive environments. Using this approach would double the lifespan of the key parts and components and reduce potential downtime.

In order to achieve the optimal selection of fabric, a pilot filter was implemented at the worksite to take samples of concentrate. The samples were then used to help define the proper fabric for the filtering process, given the specific mineral conditions that Collahuasi was processing. In many situations, these types of tests involve using Metso laboratories located in Brazil and Finland. However, with the pilot filter onsite, it was possible to perform all the tests in-situ with the client, improving the selection and making it easier and quicker to get results.

Another technological improvement introduced was the implementation of OCS-4D, an advanced process control solution. The solution assisted in determining the optimal control modes through analysing the interplay between the selection of fabrics and maintenance events.

Finally, the chute was examined for possible improvement opportunities. As the VPA filters discharged the filtered material (cake) into the chute, it was subjected to high rates of wear, causing a reduction in performance. Various designs and options were examined to improve ease of maintenance and reduce downtime.

“Searching for a design that improved maintainability, we implemented new, modular design upgrades to the chute so it could receive maintenance section by section,” Metso Minerals Process Equipment Manager Alejandro Bravo said.

“Thus, when a specific part shows signs of wear, we can disassemble that part and change it quickly. This is also an improvement that was tailored for the client, given that with the original design we had to disassemble the entire equipment to be able to change some parts.”

Expansion of the project to all VPA filters

 Given the success of the project, Minera Doña Inés de Collahuasi SCM is evaluating the implementation of the same upgrade concept in other VPA filters as part of its asset management plan.

“With this solution, we have been able to meet some of the availability goals we set for 2017,” Collahuasi Senior Engineer for Symptomatic Process Cristián Barros said. 

“The filter today works according to the plans drawn up with Metso, which helps us to continue operating efficiently.”

latest news

St George hits more nickel mineralisation

Aspiring nickel producer St George has confirmed further drilling intersections of nickel-copper sulphides across its three prospects at the Mt Alexander project about100km west of Leonora in the northern Goldfields.

Read more

Lithium Australia gets new lithium sniff in WA

Lithium Australia’s penchant to get ahead and stay ahead of the pack that is feverishly hunting for lithium in WA keeps paying off for the ASX listed lithium expert.

Read more

BHP uses laser tech to speed up shiploaders

BHP is harnessing the same cutting-edge laser technology used in driverless cars at its port operations in Port Hedland.

Read more

Johnston wary of Govt role in battery production

WA Mines Minister Bill Johnston has greeted with caution a mining industry report calling on governments to take a bigger role in securing WA’s stake in the looming global electric vehicle revolution.

Read more

WesTrac to unveil 'most advanced excavators ever'

They don’t quite drive themselves but at the rate Caterpillar is developing its kit, it is only a matter of time before they do.

Read more

Elon Musk’s Tesla moves in on WA lithium

Kidman Resources has struck a binding offtake deal with Elon Musk’s Tesla for the supply of lithium hydroxide to be used in the batteries that power the company’s electric cars. 

Read more

 

industry insight

Tracking the trends into 2018 and beyond

The future is full of change for the mining sector, according to Deloitte’s Tracking the Trends

...
Products & Technology

Collaborate and plan

People & Projects

Fuchs goes big in at Beresfield 

Occupational Safety & Health

Two-pronged approach to frontline innovation 

interview

A fleeting opportunity

Western Australian Chief Scientist Professor Peter Klinken believes the time is now for battery metals.

Read more